Green power push gets grid backing
New Delhi: India is seeking to better align transmission infrastructure with generation projects, particularly renewable energy capacity additions, after delays in power evacuation infrastructure in some states because of implementation challenges. The Central Electricity Authority (CEA) has issued standard implementation timelines for interstate transmission system (ISTS) projects.Transmission projects typically take 36-60 months to complete, while renewable energy projects are usually commiss…